Nov 22, 2021

CONSIDERATION OF POLE ATTACHMENT AGREEMENT

Item 10: Consideration of Pole Attachment Agreement with Rocky Mount Housing Authority (outlines terms and conditions for attachment of security cameras on thirty-four [34] utility poles [31 poles owned by City; 3 poles

Nov 22, 2021

CONSIDERATION OF BID

Item 12: Consideration of 1) Bid – 230 kv Circuit Switcher for South Point of Delivery Station – award to RW Chapman & Company @ total cost of $121,390; and 2) FY 2021-2022 Budget Amendment

Nov 22, 2021

CONSIDERATION OF THE FOLLOWING BIDS

Item 13: Consideration of the following Bids: a) Architectural Services for City Hall Interior Renovations – 1st Floor (South Side) – award to Oakley Collier Architects @ total cost of $120,000 (contractor will subcontract 20%